From the Dračevac Construction Site: Works on the Central Building of the Future Technology Park Proceeding to Plan

Today, Mayor Ivica Puljak and his associates toured the site of the future Split Technology Park – Dračevac building, where works on the reconstruction and extension of the central building are proceeding according to schedule.

The tour was led by representatives of the contractor, Strabag d.o.o.: chief site engineer and project manager Veljko Grbeša, and Marin Knežević, contractor’s representative and team leader. Earthworks, reinforced concrete works, masonry, tiling, plasterboard, insulation and installation works, as well as works on the aluminium and glass façade, are currently under way on the site.

The cumulative value of works completed up to and including June amounts to €6,722,742.50 excluding VAT, while the contracted value of the works is €16,602,910.61.

The building is expected to be completed at the end of December this year, when, according to the Works Schedule, the technical inspection is planned.

As a reminder, the projects Construction and Equipping of the Central Building of Split Technology Park – Dračevac and Development of the Dračevac Zone – Split Technology Park – Dračevac are financed by the European Regional Development Fund. The project holder is the City of Split, and the project runs from December 2020/January 2021 to December 2023. The total value of the project is HRK 164,754,315.70 / €21,866,655.47, of which EU grants amount to HRK 105,074,234.69 / €13,945,747.52.