Progress on the Reconstruction and Extension of the Central Building of the Future Split Technology Park

Works on the reconstruction and extension of the central building of the future Split Technology Park are being carried out on the site of the former Dračevac barracks. Works are under way section by section across the expansion joints – earthworks, reinforced concrete works and installation works – alongside the preparation of the detailed design. By the end of January, certain insulation works had been completed, as well as electrical installation works, fire suppression installations, ventilation, heating and cooling installations, and water supply and drainage works.

The cumulative value of all works completed by the end of January 2023 amounts to €3,187,153.03 excluding VAT (HRK 24,013,604.50), and the building is scheduled for completion in December this year.

The removal of the existing building and the construction of the central building of the Technology Park are being carried out by Strabag d.o.o., and the value of the construction of the central building of Split Technology Park – Dračevac is HRK 124,498,144.27 / €16,523,743.35.

As a reminder, the projects Construction and Equipping of the Central Building of Split Technology Park – Dračevac and Development of the Dračevac Zone – Split Technology Park – Dračevac are financed by the European Regional Development Fund. The project holder is the City of Split, and the project runs from December 2020/January 2021 to December 2023.

The total value of the project is HRK 164,754,315.70 / €21,866,655.47, of which EU grants amount to HRK 105,074,234.69 / €13,945,747.52.